Albion undertook the CQA work for GR Service Company\’s new borehole installations in Falkirk in conjunction with Halcrow. The engineering works
for the installations started in September 2005 and were complete by October 2005. The CQA work provides the assurance and validation for each of the elements of the installation. The CQA for the engineering works must ensure levels conform to the design at all stages of construction as well as the quality and consistency of all materials used. This information was essential to allow GR Services and there consultant Halcrow to prepare and submit their PPC application.